Saluran Air di Jl Asem Ciracas Direvitalisasi

Jalan Asem Channel Normalization to Finish by End of July

Eight personnel are working on the normalization of a 60-meter channel along Jalan Asem, RT 10/09, Ciracas Urban Village.

It is targeted for completion within 40 working days

Ciracas Sub-district Water Resources Executing Unit Head, Yulia Indah stated that the normalization project uses 40x40x120 cm U-ditch concrete, complete with concrete cover slabs.

"The work has been underway since last Monday (6/15), and it is targeted for completion within 40 working days, or by the end of July," she expressed, Saturday (6/20).

Krukut River to Be Normalized to Address Flood in Kemang

According to her, the old 20-centimeter-wide red-brick channel could no longer accommodate the water discharge during rainfall, often resulting in localized flooding.

Ciracas Urban Village Head, Arifin commended the East Jakarta Water Resources Sub-agency personnel for their prompt response to residents' requests to renovate the channel.

"Thankfully, the normalizartion is now a reality. We would like to thank and commend the team for following through on this community request," he concluded.

Linked News
Popular News indeks
  1. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye755 personDessy Suciati
  2. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye548 personAldi Geri Lumban Tobing
  3. 1,500 Runners and Pets Hit the Track for World Rabies Day Run 2026

    access_time03-10-2026 remove_red_eye543 personAnita Karyati
  4. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye526 personFakhrizal Fakhri
  5. Jakarta Logs 0.13% Inflation as Chicken, Chili, and Rice Push Prices Up

    access_time03-10-2026 remove_red_eye507 personFakhrizal Fakhri