Jalan Asem Channel Normalization to Finish by End of July

Eight personnel are working on the normalization of a 60-meter channel along Jalan Asem, RT 10/09, Ciracas Urban Village.

It is targeted for completion within 40 working days

Ciracas Sub-district Water Resources Executing Unit Head, Yulia Indah stated that the normalization project uses 40x40x120 cm U-ditch concrete, complete with concrete cover slabs.

"The work has been underway since last Monday (6/15), and it is targeted for completion within 40 working days, or by the end of July," she expressed, Saturday (6/20).

Krukut River to Be Normalized to Address Flood in Kemang

According to her, the old 20-centimeter-wide red-brick channel could no longer accommodate the water discharge during rainfall, often resulting in localized flooding.

Ciracas Urban Village Head, Arifin commended the East Jakarta Water Resources Sub-agency personnel for their prompt response to residents' requests to renovate the channel.

"Thankfully, the normalizartion is now a reality. We would like to thank and commend the team for following through on this community request," he concluded.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1923 personFakhrizal Fakhri
  2. Pramono Vows to Prioritize Jakarta’s Strategic Development

    access_time22-08-2026 remove_red_eye994 personDessy Suciati
  3. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye749 personDessy Suciati
  4. Rano: CIEIE 2026 to Catapult Jakarta’s MSMEs onto the International Stage

    access_time25-08-2026 remove_red_eye708 personBudhi Firmansyah Surapati
  5. Pramono Pushes for Partnership Between New Toto Tentrem and Tarakan Hospitals

    access_time24-08-2026 remove_red_eye629 personDessy Suciati